No holiday rest as big Mt Eden milestone nears for City Rail Link

Auckland-New-Zealand

Auckland, City Rail Link, new zealand,

1823 views

The country’s largest transport infrastructure project is taking advantage of an almost complete closure of the rail network’s Western/North Auckland Line to make significant changes around the site of the old Mt Eden Station.

“The closure gives us the momentum for our teams to complete big and necessary work around the rail corridor safely without having to worry about trains” says Dale Burtenshaw, North Auckland Line Construction Manager for the Link Alliance. “We’re mindful of our neighbours and we have measures in place to minimise any disruption.”

KiwiRail’s closure, known as a Block of Line, runs from Boxing Day, 26 December, until 23 January. During this time, CRL’s additional work hours will include weekends, public holidays and nights.

The essential part of the holiday work programme involves switching 1.3 kilometres of track. The existing single line through the station site will be removed and trains travelling in both directions switched onto a new section of track. The switch is one part of a construction programme to connect the Western Line with CRL at a redeveloped Mt Eden Station.

We’ve got a very tight timetable to do all this – lift the existing track, making the switch and commissioning the new track, and completing construction work for the CRL lines,” Mr Burtenshaw says. “This is significant milestone for the project and needs to be finished by around 12 January with an overnight train running the length of the newly laid track for the first time.”

In addition to the track work, some civil construction activity will also continue on the Mt Eden site.

“We’re very aware that we work close to homes and businessess and we will do all we can to manage noise, dust and vibration,” says Mr Burtenshaw.

“Our experts will continue to closely monitor environmental impacts and install mitigation measures where required. Noise mats will be used where possible around work sites and equipment, and water misters and cannons will be used to dampen the material and reduce dust. Lights used during any night works will be angled down directly onto the work site to avoid light spill to surrounding properties.”

View the media release here

^ Back to top