First stage of excavating the HS2 Chiltern tunnels completed

HS2 cross passage

Align JV, cecilia, construction, HS2, tunnelling,

1733 views

HS2’s main contractor, Align JV, accomplishes the first out of thirty-eight underground connections linking the northbound and southbound tunnels.

The Chiltern tunnels will carry high speed trains between London and the North at speeds of up to 200mph (320km/h). The trains will travel through two parallel tunnels linked by short passages for use in emergencies.

With the two giant tunnelling machines – Florence and Cecilia – now almost four miles into their journeys, attention has turned to the first cross passages.

“HS2 is making huge progress, with 25,000 jobs supported by the project, construction in full swing between London and Birmingham and now the start of this new phase of tunnelling work under the Chilterns,” says HS2’s Head of Tunnel Engineering, Martyn Noak.

An expert team of miners used a remotely controlled excavator to break out and excavate from one running tunnel to the adjacent tunnel.  As the excavation progresses, the ground is supported using a sprayed concrete lining (SCL).

“While invisible to the travelling public, the cross passages have a key role in providing a safe operational railway.  In an emergency, they allow the safe evacuation of passengers into a place of relative safety – the other tunnel. Constructing cross passages is different than using a tunnelling machine, as the ground is excavated in short lengths, with each advance being left unsupported for a short period of time until the sprayed concrete lining is installed. It is a different set of risks, and a specific skilled workforce is needed.” says Martyn Noak.

Delivered by HS2’s main works contractor, Align – a joint venture formed by Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick – each passage is between 15 and 20 metres in length.

“In partnership with our supply chain; KVJV responsible for the ground treatment, specialist contractor Euro Diamond Drilling and waterproofing specialist Rennesco, the sub-surface team at Align have already commenced preparation work on several other cross passages and are making good progress,” says Align’s Project Director, Daniel Altier.

Once the team had completed the SCL-lined tunnel, a water-proof membrane was installed, followed by a secondary concrete lining constructed by placing concrete behind formwork in the cross passage.

Once the passageway is complete, the safety doors can be installed at either end. These are being manufactured by Bolton-based Booth Industries, who won the contract to provide more than 300 units for all the tunnels between London and Birmingham.

The win allowed Booth Industries to establish a new facility in the town and create up to 50 jobs over the next ten years. The sliding doors have been subjected to rigorous fire and fatigue testing to take account of the train speeds, associated pressures and frequency of the trains. 

Each running tunnel has an emergency walkway that allows passengers to safely evacuate the train and walk through the cross passages into the other tunnel, where they can be rescued on a passenger train.  Access to emergency services is from the portal or one of the five ventilation/emergency access shafts.

Source: © High Speed Two Ltd 2022

Image source: © High Speed Two Ltd 2022

^ Back to top